Answer by
nprabakaranrocketmailcom (13)
It is one of the construction work wherein the necessary water pipes,drainage pipes, and other vents like electrical tubings are installed before the concrete roofings setup and before the walls in and around the building are closed. The erected fixtures are to be tested before they are covered by plastering.